Beyerford Heights Main Replacement Project
This project involved the installation of 7,700 feet of new 12” water mains and 12,000 feet of 8” water mains. A total of 48 fire hydrants were either replaced or upgraded as part of this project. In addition, approximately 282 meters were installed, including new house service lines to the residences. The project is bounded by Marconi Avenue, Mission Avenue, El Camino Avenue, and Eastern Avenue.
Construction was completed in November 2008. The total project cost was $3.9 million.
Click here to print the pdf version of this project. | |
The PDF files require you to have the free Adobe Acrobat Reader on your Computer
Click the "Get Acrobat Reader" graphic to go to the Acrobat Reader page on Adobe' web site.
|
|