The project consists of the installation of new water distribution main pipeline in public streets to replace existing backyard water mains that have outlived their useful life.

Major project facts:

  • 22,860 feet of 6-, 8-, and 12-inch diameter pipe is to be installed
  • 70 fire hydrants will be upgraded.
  • 250 new metered services will be installed; and 100 meters will be reconnected.
  • The construction cost is estimated to be $8 million.

Schedule:

  • The project began in December 2017 and is expected to be completed in the fall of 2018.
  • Final street restoration is anticipated in the spring of 2019 (warmer temperatures are necessary for this type of work).
  • January Work Phases (see map below):
    • Main Replacement - Phase  11 (Doug Veerkamp General Engineering, Inc.)
    • Service Line and Meter Installation - Phase 11 (Flowline Contractors, Inc.)

 Edison Meadow Phasing Map

Download the pdf version of the project area map

Main Replacement FAQs.

Contact Information:

After-hours emergency calls should be directed to SSWD's main number 916.972.7171.

Construction Manager (primary contact)
      ERC Contracting (contractor for SSWD)
      Ricky (Richard) Ingraham
      Phone: 916.768.0786
      Email: erccontracting@yahoo.com

Field Inspector
      S. E. Ahlstrom Inspection (contractor for SSWD)
      Scott Ahlstrom
      Phone: 916.849.7159
      Email: seahlstrom@yahoo.com

Project Manager
      Sacramento Suburban Water District
      David Espinoza, P.E.
      Phone: 916.679.2886
      Email: despinoza@sswd.org